ORDER-SHEET

IN THE HIGH COURT OF SINDH, CIRCUIT COURT LARKANA

Constt. Petition No. D- 440 of 2010.

 

Date of hearing

Order with signature of Judge

03.10.2012.

 

1.                 For order on office objection.

2.                 For Katcha Peshi.

3.                 For order on M.A. No. 1051/2010.

4.                 For order on M.A. No. 3211/2012.

 

Mr. Rashid Mustafa Solangi, Advocate for petitioner.

Mr. Muhammad Ashique Dhamraho, Advocate for respondent No.3.

Mr. Imtiaz Ahmed Soomro, Asstt. A.G, assisted by Mr. Ali Raza Pathan, State Counsel, alongwith Mr. Abdul Ghafoor Soomro, Executive Engineer, Larkana Drainage Division, Larkana/Respondent No.1.

~~~~

 

          For detailed reasons to be recorded latter, present petition is disposed of in the following terms.

 

          Heard learned counsel for the parties and Mr. Abdul Ghafoor Soomro, Executive Engineer, Larkana Drainage Division, Larkana/respondent No.1, who has filed an undertaking before this Court that he will approach and move the proposal to the Government of Sindh, for construction of slap cover over the retaining wall along 2R Sub Drain of Larkana South System @ RD-8 + 700 to 13+00; and action would be made through law enforcing agencies for removal of illegal and unauthorized construction of shops and gates on the Government property along 2R Sub Drain of Larkana South System. He further undertakes that he shall complete the exercise mentioned in the undertaking within fifteen days from today.

 

          Alongwith the comments filed by respondent No.1, a site plan of 2R Sub Drain of Larkana South System  @ RD-8 + 700 to 13+00 marked in green color, has been annexed. The respondent No.1   in his undertaking undertakes to remove encroachment from the green portion of the site plan, as it is reserved for plantation. The respondent No.1 is directed to immediately approach S.S.P Larkana, in order to remove illegal and unauthorized encroachments from the aforementioned area. The S.S.P, Larkana, is directed to take action in accordance with law for the removal of the encroachment from the area pointed out by the respondent No.1. This exercise to be completed within two week’s time from today.  After completion of exercise stated above, the respondent No.1 and the S.S.P, Larkana, are directed to submit their compliance report in this Court through Additional Registrar of this Court.

 

 

                                                                Judge

 