ORDER SHEET
IN THE HIGH COURT
OF SINDH BENCH AT SUKKUR
Date of hearing |
Order
with signature of Judge |
1.
For hearing of CMA No.581/2010
2.
For hearing of main case
(Learned
counsel for applicants has not complied with the Court order dated 17.08.2017).
(Notice
issued to respondents)
17.08.2018
Mr. Mujeeb-ur-Rehman Soomro, Advocate
for the applicants.
Mr.
Abdul Ghaffar Memon, State
Counsel.
.-.-.-.-.-.-.-.-.-.-
The only question
left in this revision application is as to whether the applicants are entitled
for the interest on the amount determined by the Land Acquisition Officer in
pursuance of a judgment and decree passed in Land Acquisition Suit No.1/1989.
Learned State
Counsel submits that the Executing Court cannot go beyond decree and since the
decree is absolutely silent to the extent of future interest, therefore, the Executing
Court cannot pass order for the payment in addition to what is stated in the decree.
Learned State Counsel has relied upon the case of Karachi Water and
Sewerage Board through Managing Director v. Messrs
Famous Art Printers (Pvt) Ltd. through Director and the case of Industrial
Development Bank of Pakistan through Vice-President I.D.B.P. v. Messrs Crystal Chemicals Limited through Director /
Guarantor Chrystal Chemical Ltd. and 9 others reported in PLD 2016
Sindh 527 and PLD 2009 Lahore 176, respectively. He further stated
that they have made payment over and above decretal amount.
On the other hand,
learned counsel for the applicants while arguing his case has relied upon the
contents of the judgment. The District Judge Sukkur while proceeding with Land
Acquisition Suit No.1/1989 framed issues, and the issue No.4 as framed is as under:
“ 4. Whether the plaintiff is entitled to
additional compensation at the rate of Rs.15% per annum from the date of the
notification U/S 4 of the Land Acquisition Act, as provided by S.28 of the Land
Acquisition Act as amended by Sindh Ordinance, 23 of 1984. ”
This substantially
is in respect of the compensation at the rate of 15% per annum in terms of
Section 28/28(a) of the Land Acquisition Act, 1894. While relying on the
findings on issue No.4, learned counsel for the applicants submits that the compensation
in terms of the findings on issue No.4 was awarded till the date of payment of
compensation.
I have heard the
learned counsel and perused the material available on record. The precise
question is a claim of interest over the amount of compensation that is
compulsory acquisition charges and additional compensation at the rate of 15%
per annum. The provisions related to compulsory acquisition and additional
charges talks about the payment at the rate of 15% per annum to be paid from
the date of notification under Section 4 to 11 to the date of payment of
compensation. Thus, the jurisdiction of the Land Acquisition Officer originates
from these provisions which empowered him to grant compensation from the date
of notification till the payment is realized or deposited in Court.
The judgment available as passed in Land
Acquisition Suit No.1/1989 also talks about the grant of decree along with 15%
compulsory acquisition charges and 15% additional compensation charges
from date of notification. However, decree does not talk about its realization
till the payment is deposited. These findings in the shape of issue No.4 read
with decree could hardly be interpreted in favour of the respondents as the law
requires compensation and additional charges to be made from the date of
notification till the payment is realized or deposited in Court. Even
otherwise, the decree itself shows the calculation of interest till the date of
its issuance. Hence, it cannot be interpreted to be without future interest
till it is realized. The jurisdiction of the Land Acquisition Officer passing
the decree originates from the law which only empowered him to grant decree
along with such compensation till it is realized and not otherwise. No doubt a
sum of Rs.2,45,194/- was adjudged to be unpaid in the year 2010 but it was paid
and deposited on 29.05.2016. Now it is to be seen whether amount of interest
also paid or adjusted. One of the judgments cited by the learned State Counsel
in the case of Muhammad Afzal and another v. Pakistan International
Airlines Corporation reported in 2006 YLR 3074 also laid down a
principle that where in the implementation and execution of a decree, the question
of its interpretation was involved then it was for the Executing Court to
examine the relevant record to conclude exact nature of reliefs allowed to a
party on the basis of a decree framed in a suit. The relevant para is
reproduced as under:
“ 17. In
our opinion, it should always be the approach of the Courts of law that
multiplicity of litigation should be avoided for mere hypertechnical
reasons, and further while interpreting a document the Courts instead of giving
effect to weight to its substance to give effective and substantive reliefs to
the parties in litigation. Both the learned counsel are in agreement on the well recognized proposition of law that the scope of
Executing Court is limited to the extent that it cannot go behind the decree
but the fact remains that where in the implementation and execution of a decree
the question of its interpretation is involved then it is for the Executing
Court to examine the relevant record to conclude exact nature of the reliefs
allowed to a party on the bais of decree framed in a
suit. As observed above plain reading of prayer clause (b) of the decree under
execution reveals that it was only the first part of such prayer, which was
declaratory in nature while the consequence of such declaration was
incorporated in the second part that the petitioner is entitled to pension and
other benefits. If we agree to the arguments of Mr. Amir Malik that the decree
under execution to the extent of prayer clause (b) is only declaratory in
nature, it will mean that though the petitioner has succeeded in his prolonged
litigation of over twenty years with the respondent but practically he has
gained nothing out of it which obviously cannot be his intention in filing of
the suit or of the petitioner in the terms that “suit is decreed as prayed”.
Thus, we are of the considered opinion that by virtue of the decree under execution,
the petitioner is not only entitled for the sum of Rs.46,000 towards the
provident fund as prayed in the prayer clause (d) of the decree but also other
lawful benefits of retirements, excluding those which were given up by him in
terms of his application under Order XXIII, rule 1, C.P.C. dated 18‑7‑1984
moved before the Appellate Court in Civil Appeal No.162 of 1983. ”
Hence, I dispose
of this matter with the direction that the Executing Court shall rehear the
parties and adjust and calculate the amount deposited by judgment debtor
keeping in mind that decree holder is entitled to claim interest over the
amount decreed in terms of issue No.4 of the judgment. The amount of interest
is payable on the unpaid principal amount till its realization.
The Executing Court may, however, adjust
all such payment made by the judgment debtor and in case the principal amount
has already been paid along with interest to any date, then no future
compensation along with interest is required to be paid except the outstanding
interest amount. The amount will be released to the decree holder only after
aforesaid adjustments.
J U D G
E
Abdul Basit