JUDGMENT
SHEET
HIGH
COURT OF SINDH, BENCH AT SUKKUR
Before
Mr. Justice Syed HasanAzhar Rizvi
Mr.
Justice Muhammad Humayon Khan
C.P.
Nos. D- 1074 & 1075 of 2016
|
PETITIONERS |
: |
Syed
Muhammad Ismail Shahand another through Mr. Syed Jaffar Ali Shah, Advocatealongwith
Attorney of the petitioners Syed Mureed Ali Shah |
|
RESPONDENTSNOS.1,
3TO6 |
: |
Pakistan
through Secretary Communication & Works and others through Mr. Ahmed Ali
Shahani, AAG |
|
RESPONDENT
NO.7 |
: |
M/s.
Hussain Construction Company (not represented) |
|
RESPONDENTNO.2 |
: |
Chairman
National Highway Authoritythrough Mr. Khan Muhammad BangashAdvocate. |
|
DATE
OF HEARING |
: |
14.03.2017 |
|
DATE
OF JUDGMENT |
: |
14.03.2017 |
JUDGMENT
Muhammad Humayon Khan, J:Initially,
the petitioners filed Civil Revision Applications Nos. 32 and 33 of 2004
against the common Order dated 29.03.2014 passed by the learned IInd Additional
District Judge, Khairpur, in Civil Appeals Nos.29 and 30 of 2014, whereby, two
Orders dated 26.02.2014 passed by the learned Senior Civil Judge, Gambat, on
two applications namely (i) Application for re-opening of execution application
and (ii) Application for increasing/re-calculating the decreetal amount from
Rs.94,46,870/- to Rs.14,37,62,481/- were set-aside. Later on, by Order dated
14.03.2016 both the said civil revision applications were converted into above
constitution petitions. Since, the facts and legal points are same, we intend
to decide both the petitions by this common Judgment.
2) The relevant facts for the disposal of these
petitions are thaton 24.12.2001, petitioners filed a Civil Suit No. 41of 2001
for declaration, compensation and permanent injunction against the respondents pleading
therein that in the year 1993, the respondents acquired an area of 3.05 acres
of their land having petrol pump etc. over it, for construction/extension of
National Highway and for this purpose, Notification under Section 4 of the Land
Acquisition Act, 1874 (hereinafter referred to as “the said Act”) was issued on
25.11.1993, which was followed by another Notification under Section 6 of the
said Act and taking over of possession
of acquired land on 25.01.1994, but as yet no Award has been made and no
compensation has been paid to them for their lawful acquired land. The suit was
contested between the parties and ultimately the suit of the petitioners was
decreed as prayed by the Trial Court vide Judgment dated 10.05.2005,which was
challenged by the respondents in Civil
Appeal No.51 of 2005 before the learned Additional District Judge, Gambat, who
dismissed the said appeal vide Judgment dated 13.04.2006. The concurrent
findings of the two Courts below were thereafter challenged by the respondents
before this Court in Civil Revision No.75 of 2006, which was also dismissed
vide Judgment dated 20.07.2009. Against the concurrent findings of three Courts
below, the respondents filed Civil Appeal No.38-K of 2010 before theHon’ble
Supreme Court,which was dismissed by Order dated 17.05.2013 being devoid of
merits. After dismissal of the said appeal by the Hon’ble Supreme Court, the petitioners
filed two applications under Section 151 CPC before the Executing Court,
whereby Execution Application was reopened and decreetal amount was re-calculated
by Orders both dated 26.02.2014, which were challenged before the learned 2nd
Additional District Judge, Khairpur, in Civil Appeals Nos. 29 and 30 of 2014,
which were allowed by the impugned Orders and Orders of the Executing Court were
set- aside. Against the common impugned Orders, the petitioners have filed the
instant petitions.
3) We have heard the learned counsel for the petitioners
and respondentsas well as learned AAG and perused the material available on
record.
4) The learned counsel for the petitioners
contended thatsince the Execution Application was pending for sufficient time,
therefore, Executing Court was competent to pass an order reopening the same
when no appeal was pending before any higher Court. He further contended that
the Trial Court had not calculated the real amount of compensation at the time
of deciding suit and now the Executing Court has correctly calculated the
compensation amount. He further contended that valuable land and petrol pump of
petitioners had gone under the construction of Road and respondents had not
paid the compensation amount calculated by the Executing Court and filed
appeals before appellate Court to avoid paymentof the said amount although
neither the calculation of amount by the Executing Court is illegal nor the Orders
passed by the ExecutingCourt on applications under Section 151 CPC. In support
of his contentions, learned counsel for petitioners relied upon the following
case-law:-
i)
Syed
Saadi Jafri Zainabi Vs. Land Acquisition Collector and Assistant Commissioner
(PLD 1992 Supreme Court 472);
ii)
BP
Pakistan Exploration and Production, through AttorneyVs.Sher Ali Khawaja and
another (PLD 2008 Supreme Court 400);
iii)
Imamuddin
Shah through AttorneyVs. Deputy District Officer (Rev.) and Land Acquisition CollectorSanghar
and another (2005 MLD (Karachi) 69);
iv)
Engineer
Jameel Ahmad Malik and 9 othersVs. Land Acquisition
Collector,Attock and 3 others (2004 MLD (Lahore) 523);
v)
AbdulQadir
and 5 othersVs. A.C./Collector, Quetta and another (2003 YLR (Quetta) 199).
5) On the other hand, the learned counsel for
respondents contended that the concurrent findings of threeCourts below in
favour of the petitioners were challenged before the Hon’ble Supreme Court by
the respondents in Civil Appeal No.38-K of 2010, which was dismissed vide Order
dated 17.05.2013 and hencethe decision attained finality. He further contended
that Execution Application filed by the petitioners before the Trial Court was
pending due to pendency of appeals, but no stay order was granted by the
appellate Court to stay the execution proceedings, therefore, Orders for
reopening the Execution Application and re-calculation of amount on
applications under Section 151 CPC were totally irregular, illegal, null and
void and the same were rightly set-aside by the learned Additional District
Judge. He further contended that Trial Court had decreed suit for compensation
of an amount of Rs.94,46,870/- and that amount was neither increased nor
decreased by any Appellate Court but the Judgment and decree passed by the Trial
Court was maintained as it is uptoHon’ble Supreme Court, as such Executing
Court was not competent to go beyond the decree, hence the Appellate Court has
rightly set-aside the Orders passed by the Trial Court on applications under Section
151 CPC by the impugned Orders.
6) The learned AAG supported the arguments
advanced by the learned counsel for the respondents.
7) We have carefully gone through the
following case-law relied upon by the learned counsel for the petitioners and
came to the conclusion that none of the said case-law is applicable to the
facts of the instant petitions in as much as all the reported cases pertain to
the land acquisition proceedings under the Land Acquisition Act, 1874 after the
Award was passed by the Land Acquisition Officer, whereas, the present case is
entirely different as neither land acquisition proceedings were commenced nor
any Award was passed but the petitioners instead of approaching the Land
Acquisition Officer to commence the land acquisition proceedings filed civil
suit, which is of civil nature and the procedure prescribed under the Land
Acquisition Act,1874 is not applicable in the civil suits:-
i)
Syed
Saadi Jafri Zainabi Vs. Land Acquisition Collector and Assistant Commissioner
(PLD 1992 Supreme Court 472);
ii)
BP
Pakistan Exploration and Production, through AttorneyVs.Sher Ali Khawaja and
another (PLD 2008 Supreme Court 400);
iii)
Imamuddin
Shah through AttorneyVs. Deputy District Officer (Rev.) and Land Acquisition CollectorSanghar
and another (2005 MLD (Karachi) 69);
iv)
Engineer
Jameel Ahmad Malik and 9 othersVs. Land Acquisition
Collector,Attock and 3 others (2004 MLD (Lahore) 523);
v)
AbdulQadir
and 5 othersVs. A.C./Collector, Quetta and another (2003 YLR (Quetta) 199).
8) It appears that after full-fledged
proceedings in the suit before the Trial Court, it was established that the
disputed land owned by petitioners was utilized by the respondents for the
construction of national carriageway of National Highway after issuing Notifications
under Sections 4 and 6 of the Land Acquisition Act, 1874, but thereafter
neither any Land Acquisition Officer was appointed nor land acquisition
proceedings were commenced and therefore no Award for compensation was passed.
Admittedly, the concurrent findings of the three Courts below were maintained
upto the Hon’ble Supreme Court. However, after dismissal of appeal by the
Hon’ble Supreme Court, petitioners moved applications under Section 151 CPC
before Executing Court and by Orders dated 26.02.2014, the Executing Court
reopened the Execution Application and increased/recalculated the decreetal
amount. Since, the matter had already attained finality and thus the Orders
dated 26.02.2014 passed by the learned Senior Civil Judge, Gambat (Executing
Court) were beyondthe powers of Executing Court and hence without jurisdiction,
null and void having no legal effect whatsoever and accordingly the same were rightly
set- aside by the Appellate Court vide impugned Orders.
9) In the case ofSardarAhmed Yar Khan Jogezai and 2 others Vs. Province of Balochistanthrough
Secretary, C & W Department reported in 2002 SCMR 122,the Hon’ble
Supreme Court has held that:-
“The said substitution or drastic amendment
could not have been made by the learned executing Court which in fact amounts
to a futile attempt to frustrate the object of Judgment and Decree dated
04.11.1985 which had already attained finality and thus the Order dated
13.04.1989 passed by the learned District Judge Loralai (Executing Court) is
arbitrary, capricious and coram-non-judice. It worth mentioning that executing Court could not go beyond the
decree. It is well‑settled by now that "when decree
passed attained finality it had got to be executed even if it was erroneously
passed. Executing Court cannot rectify any mistake in decree which would
tantamount to going behind decree." (Messrs Haji Ahmed
&. Co. v. Muhammad Siddique and others (PLD 1965 Kar. 293, GhanayaLal and
others v. Punjab National Bank Ltd., Lahore AIR 1932 Lah. 534 and Abdul Khatiq
v. Haji PLD 1983 Lahore 445). A similar proposition was discussed in case
titled Topanmal v. KundomalGangaram (AIR 1960 Supreme Court 388) that "the
executing Court could not go behind the decree and given relief to the
plaintiff which was expressly denied to him in the suit. A Court executing a decree cannot go behind the decree; it must take
the decree as it stands, for the decree is binding and conclusive between the
parties to the suit". In fact the original judgment/decreedated 21‑5‑1977
was passed by the same District Judge in the capacity as Civil Judge and,
therefore, the controversy should not have been resolved by him which aspect of
the matter has been ignored for the reason best known to the learned District
Judge himself”.
10) The learned counsel for the petitioners has
not been able to show any legal error in the impugned Orders passed by the
learned Additional District Judge, which are passed in accordance with law and
do not call for any interference by us in the constitutional jurisdiction.
11) In view of the above discussion, the instant
petitions alongwith the listed applications were dismissed by us vide short
Order dated 14.03.2017 and the above are the reasons for our said short Order.
JUDGE
JUDGE